| DeSoto Independent School District,
DeSoto |
Project Cost:
$2,885,000 |
| Hulen Hansen, Director of Plant Services |
(972) 223-8425 |
Kinsman
& Associates has performed analysis, retrofit design,
and construction monitoring at nine campuses for the DeSoto
ISD. These projects have included: designing a district-wide
energy management system (EMS), converting inefficient
lighting sources to high efficiency fluorescent luminaires
with electronic ballasts; installing reflectors, motion
detectors and photocells; replacing electrical resistance
heating rooftop package units with high efficiency natural
gas heating rooftop units; replacing an old and inefficient
hot water hydronic system with a high efficiency hot water
boiler; and changing out an old 385 Ton chiller with a
high efficiency rotary compressor chiller of the same
capacity.
|
| |